Phase I: (Aug 2007 - May 2008)
   
Phase I involved the construction of 7,600 square feet main temple, 200 parking spaces, and roadways. Phase I accomplished construction of separate sanctum sanctorums of deities, namely Lord Maha Ganapati, Lord Siva, Lord Venkateswara, and Navagraha. The Maha Mandapa (main hall) now has an approximate capacity to hold 500 people.
Start of Construction: Aug 2007
Completion of Construction: May 2008
Budget to Accomplish Phase I: $1.6 Million
Funds raised for Phase I project: $650,000 (as of April, 2011)
Bank Loan Obtained: $1.0 Million